Quality is the backbone of any piping system. At JIELI, every malleable iron fitting undergoes rigorous inspection before leaving our factory. This article outlines the key inspection methods and quality control procedures that ensure our fittings meet international standards.

1. Visual Inspection (外观检查)

The first step in quality control is a thorough visual examination. Each fitting is checked for:

💡 Tip: A magnifying glass or 10× loupe is used to inspect thread profiles and detect micro-cracks on critical fittings.

2. Dimensional Inspection (尺寸检测)

All fittings must conform to the dimensional requirements of the applicable standard (BS EN 10242, ASME B16.3, ISO 49, etc.). Key measurements include:

DimensionInstrumentTolerance
Center-to-face (elbow/tee)Vernier caliper / CMM±0.5 mm
Thread pitch diameterThread plug gauge (GO/NO-GO)Per standard class
Overall lengthDigital caliper±1.0 mm
Wall thicknessUltrasonic thickness gauge≥ min. specified
Hexagon/ Square dimensionsGauge / Caliper±0.3 mm

3. Thread Gauge Inspection (螺纹规检验)

Thread quality is critical for leak-free connections. Every fitting is tested with:

⚠️ Note: BSPT (taper) threads are tested differently from BSPP (parallel) threads. NPT uses a 60° thread angle while BSPT uses 55° — the gauges are not interchangeable.

4. Mechanical Property Testing (机械性能测试)

Malleable iron fittings must demonstrate adequate strength and ductility:

TestMethodStandard Requirement
Tensile strengthTensile testing machine≥ 300 MPa (min)
ElongationTensile testing≥ 6% (K330 / EN 10242)
HardnessBrinell (HB) or Rockwell (HRB)≤ 150 HB
Burst pressureHydrostatic pressure test≥ 4× rated pressure

5. Pressure Testing (压力测试)

For fittings used in high-pressure applications, hydrostatic pressure tests are conducted:

6. Coating & Galvanizing Inspection (镀层检验)

Galvanized fittings are tested to ensure corrosion resistance:

7. Sampling & AQL Standards (抽样标准)

Our QC team follows ANSI/ASQ Z1.4 (AQL) sampling plans:

Lot SizeSample SizeAccept (Major Defects)Reject
Up to 500 pcs20 pcs01
501 – 10,000 pcs80 pcs12
10,001+ pcs125 pcs23

Critical defects (cracks, leaks, wrong thread) have zero tolerance — any single defect results in full lot rejection.

8. Certificate of Compliance

Each shipment at JIELI is accompanied by a Certificate of Conformance (COC) that documents:

✅ JIELI Promise: Every fitting we ship is traceable to its production batch. We provide full inspection reports upon request. Contact us for certified quality documentation.

By following these rigorous inspection procedures, we ensure that every JIELI fitting delivers reliable performance, safety, and longevity in the field.